Assignment of construction contracts
Assignment is the right to transfer 'choses in action' defined as 'all personal rights of property which can only be claimed or enforced by action and not by taking physical possession'.
This definition includes benefits arising under a construction contract such as right to payment, but not burdens such as the obligation to pay. The definition also includes claims for breach of contract.
A common error is to assume that the right to assign must be agreed as part of a contract, like a novation. Assignment is a unilateral right created by statute, Section 136 of The Law of Property Act 1925 or by the law of equity (law developed by the Chancery Division of the High Court of England and Wales).
Whilst not a contractual right, the right to assign can be excluded, or restricted, by contract, for example, it is common in collateral warranties to restrict to one assignment without the written permission of the warrantor.
Under Section 136 of The Law of Property Act 1925 the formalities required to create an effective legal assignment are:
- An absolute (i.e. not part of a debt or by way of charge only) assignment in writing signed by the assignor.
- A debt or other legal right of action.
- Express notice in writing to the debtor (no particular form of wording is necessary).
An assignment which fails to comply with the above formalities may, nevertheless, still be effective as an equitable assignment. Indeed an equitable assignment may be verbal. There is no substantial difference between legal and equitable assignments (though, of course it will be easier to prove a legal assignment), there are, however, procedural differences.
The assignee of a legal assignment sues the debtor in the assignee's own name. The assignee of an equitable assignment of a legal chose in action or an equitable chose that is not absolute, must join the assignor (as claimant if the assignor agrees, or defendant if not ) into any legal proceedings.
The effect of a legal or equitable assignment is to put the assignee in the same position as the assignor in respect of the benefits (not burdens) arising from the original transaction with the debtor. Consequently:
'... a debt which accrues due before notice of assignment is received, whether or not it is payable before that date, or a debt which arises out of the same contract as that which gives rise to the assigned debt, or is closely connected with that contract, may be set off against the assignee.'
(Ref. Business Computers Ltd v Anglo African Leasing Ltd.)
A counterclaim for unliquidated damages may also be set off by the debtor, but only to the value of the assigned debt. Further when there have been successive assignments the debtor cannot set off against claims by the ultimate assignee, counterclaims which the debtor has against intermediate assignees.
The Scottish law equivalent is assignation.
[edit] Related articles on Designing Buildings
- Alienation covenant.
- Appointing consultants.
- Assignation.
- Assignment of choses in action.
- Assignment of debt.
- Construction contracts.
- Difference between assignment and novation.
- Difference between collateral warranties and third party rights.
- Legal and equitable assignment.
- Novation.
- Novation agreement.
- Privity of contract.
- Privity of title.
- Proprietary information.
- Recovery of third party losses.
- Reliance letter.
- Restrictions on assignment.
- Reverse premium.
- Set off.
- The Contracts (Rights of Third Parties) Act.
- Title.
- Warranty.
[edit] External references
Featured articles and news
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA has launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments